Data centers in Egypt
34 data centers are listed in Egypt. The cities with the most listings are Cairo (20), Giza (6), Alexandria (2), Bany Swaif (1) and Maadi (1); together they hold 88% of them. The operators with the most listings are Etisalat Misr (e& Egypt) (4), Telecom Egypt (4) and National Bank of Egypt (NBE) (3), out of 22 named operators.
By type, the listings in Egypt are 65% enterprise, 21% colocation and 15% unclassified. Across all listed countries the enterprise share is 16%.
Worldwide, Egypt ranks 38th of 152 countries by number of listings, with under 1% of all listed facilities. It has the most listings in Northern Africa, ahead of Morocco (32), Tunisia (9) and Algeria (5).
The three operators with the most listings hold 32% of them; 18 of the 22 named operators have a single listed facility here. 29 facilities hold an Uptime Institute Tier certification (27 Tier III, 1 Tier II and 1 Tier IV). Tier IV: Maadi Datacenter.
32 of 34 facilities have coordinates.
Cities
Cairo (20) · Giza (6) · Alexandria (2)
Markets
Cairo (27)
Facilities
Operators
| Operator | Facilities |
|---|---|
| Etisalat Misr (e& Egypt) | 4 |
| Telecom Egypt | 4 |
| National Bank of Egypt (NBE) | 3 |
| Egypt Post | 2 |
| 7tteam | 1 |
| Abu Dhabi Commercial Bank (ADCB) Egypt | 1 |
| Administrative Capital for Urban Development (ACUD) | 1 |
| Agricultural Bank of Egypt | 1 |
| Arab African International Bank | 1 |
| Arab Bank Egypt | 1 |
| Central Bank of Egypt | 1 |
| Commercial International Bank (Egypt) S.A.E | 1 |
| Egyptian Banks Company for Technological Advancement EBC, SAE | 1 |
| Etisalat | 1 |
| First Abu Dhabi Bank Misr | 1 |
| Ministry of Communications and Information Technology (MCIT) | 1 |
| National Bank of Kuwait - Egypt Plc. | 1 |
| National Company for Telecommunication Services (NCTS) | 1 |
| TEData Company | 1 |
| Talaat Moustafa Group (TMG) | 1 |
| Vodafone Egypt | 1 |
| Vodafone International Services LLC | 1 |
Uptime Institute certified data centers in Egypt
| Facility | Operator | Certification |
|---|---|---|
| Maadi Datacenter | Egypt Post | Tier IV (Certification of Design Documents) |
| AAIB One-Ninety Headquarter Main Data Center, Room LG038 | Arab African International Bank | Tier III (Certification of Constructed Facility; Certification of Design Documents) |
| ABE Data Center 1 | Agricultural Bank of Egypt | Tier III (Certification of Design Documents) |
| Bany Swaif Data Center 1, Phase 1 | Etisalat Misr (e& Egypt) | Tier III (Certification of Design Documents) |
| Borg El Arab Data Center | National Bank of Egypt (NBE) | Tier III (Certification of Design Documents; M&O Stamp of Approval) |
| Borg Elarab Data Center 1, Phase 1 | Etisalat Misr (e& Egypt) | Tier III (Certification of Design Documents) |
| CBE DT Data Center | Central Bank of Egypt | Tier III (Certification of Design Documents) |
| CIB Main DC "SVDC | Commercial International Bank (Egypt) S.A.E | Tier III (Certification of Constructed Facility; Certification of Design Documents; M&O Stamp of Approval) |
| City Operation Center (COC) Project Building, Capital Data Center (CDC), Phase 1 | Administrative Capital for Urban Development (ACUD) | Tier III (Certification of Constructed Facility; Certification of Design Documents) |
| EBC HQ Data Center | Egyptian Banks Company for Technological Advancement EBC, SAE | Tier III (Certification of Design Documents) |
| El Shorouk 2 Data Center | Telecom Egypt | Tier III (Certification of Design Documents) |
| FABMISR Green Edge Data Center | First Abu Dhabi Bank Misr | Tier III (Certification of Design Documents) |
| HQ 6th of October Data Center Colocation | Vodafone Egypt | Tier III (Certification of Design Documents) |
| MCIT Data Center, Node 1 | Ministry of Communications and Information Technology (MCIT) | Tier III (Certification of Design Documents) |
| Mokattam Data Center | Etisalat Misr (e& Egypt) | Tier III (Certification of Design Documents) |
| NBKE-HQ-New Administration Capital Data Center | National Bank of Kuwait - Egypt Plc. | Tier III (Certification of Design Documents) |
| NCTS Tibasat Earth Station Data Center | National Company for Telecommunication Services (NCTS) | Tier III (Certification of Design Documents) |
| New Cairo Data Center | Arab Bank Egypt | Tier III (Certification of Design Documents) |
| Noor City Brain | Talaat Moustafa Group (TMG) | Tier III (Certification of Design Documents) |
| Plaza Data Center | National Bank of Egypt (NBE) | Tier III (Certification of Design Documents; M&O Stamp of Approval) |
| Sherif Data Center | National Bank of Egypt (NBE) | Tier III (Certification of Design Documents; M&O Stamp of Approval) |
| Smart Village Area 2 DC | Etisalat Misr (e& Egypt) | Tier III (Certification of Design Documents) |
| SV Datacenter | Egypt Post | Tier III (Certification of Design Documents) |
| TEData Smart Village DC | TEData Company | Tier III (Certification of Design Documents) |
| Telecom Egypt Digital Data Center | Telecom Egypt | Tier III (Certification of Constructed Facility; Certification of Design Documents) |
| Telecom Egypt Regional Data Hub | Telecom Egypt | Tier III (Certification of Constructed Facility; Certification of Design Documents; Gold Certification of Operational Sustainability) |
| Telecom Egypt Regional Data Hub 2 | Telecom Egypt | Tier III (Certification of Design Documents) |
| VOIS EG Data Center 1 | Vodafone International Services LLC | Tier III (Certification of Design Documents) |
| ADCB Egypt Main Data Center | Abu Dhabi Commercial Bank (ADCB) Egypt | Tier II (Certification of Design Documents) |